CGN starts construction of 3.6-million-tonne/year uranium heap-leach project
The project is expected to add about 500 tonnes of annual metal uranium capacity, per CGN.

Key facts
- Design ore throughput: 3.6 million tonnes a year
- Expected added capacity after completion: about 500 tonnes of metal uranium a year, per CGN
- Test program achieved an 82% uranium leach rate, per CGN
- Swakop Uranium began developing the technology in August 2013
CGN said construction has formally started on a heap-leach project at the Husab uranium mine. The project is designed to process 3.6 million tonnes of ore a year and is expected to add about 500 tonnes of metal uranium capacity annually once built.
Heap leaching extracts uranium by applying a leaching solution to ore stacked in a heap. CGN Uranium Resources developed the process for low-grade alaskite-type ore, which the company said has dense structure and poor permeability. Those properties limit solution flow and uranium recovery; CGN said conventional agitation leaching was uneconomic for the ore and its economics fell well below the industry average.
The process targets low-grade, poorly permeable ore
Swakop Uranium, a subsidiary of CGN Uranium Resources, began developing the heap-leach technology in August 2013. It uses spraying at high initial acidity and dynamic control of the solution’s acidity during leaching. The work also addressed acid conditioning and granulation, building high ore heaps and distributing the spray evenly.
CGN said the team developed a large-area, water-saving drip-irrigation system for arid conditions, addressing high evaporation and water scarcity in the Namib Desert. The system is intended to reduce water use in production.
Tests set an 8 mm crush size and a 9 m heap height
The development program included indoor tests with 1 tonne of ore, 20-tonne bench tests and a 30,000-tonne semi-industrial test. After comparing and optimizing data from more than 100 test groups, the project team selected a crushed-ore size below 8 mm and a heap height of 9 m as its preferred parameters.
CGN reported an 82% leach rate, which it said was close to the level of traditional agitation leaching. The work also produced more than 30 technical upgrades and several invention patents. Other methods developed included sampling high heaps of tailings, real-time monitoring of fluid flow through the heap, and operating agitation leaching alongside heap leaching.
CGN said the industrial project builds on 13 years of independent development and will increase the mine’s use of its resources. The company did not give a construction completion date or project cost.
More on CGN Power