Inner dome installed at Hualong One unit 4 of Zhangzhou nuclear plant
Units 1 and 2 are in commercial operation, while units 3 and 4 remain under construction and installation.

Key facts
- Unit 4’s inner dome is about 46 meters in diameter and weighs about 470 tonnes
- The lift used a 3,200-tonne crawler crane to place the dome at an elevation of about 45 meters
- Zhangzhou is planned to have six Hualong One units
- Localization rates for equipment at the site’s four Hualong One units exceed 90%, the report says
China National Nuclear Power, the controlling investor in Zhangzhou Nuclear Power, said the inner dome was installed at Hualong One unit 4 on November 26. The lift moves the unit from civil construction into equipment installation, ahead of installation and commissioning work.
The inner dome sits at the top of the nuclear island and forms part of the reactor building’s inner containment. It helps maintain the building’s integrity and sealing. The dome, about 46 meters in internal diameter and weighing about 470 tonnes, was lifted to an elevation of about 45 meters with a 3,200-tonne crawler crane.
The project reused construction experience from Zhangzhou units 1 to 3 and used a dome-building method tested in engineering practice. Preparations included finite-element checks of lifting conditions, dedicated slings and positioning equipment, a simulated lift, a test lift to level the load, and stress monitoring.
Zhangzhou is planned to have six Hualong One units. Units 1 and 2 are in commercial operation; units 3 and 4 are under construction and installation, and preliminary work is under way for units 5 and 6. Equipment localization rates for the four units exceed 90%, the report says.