Mochovce 4 reaches 35% power, generates 16.2 GWh

Tests at the current power level must be completed and evaluated before the unit can advance to 55%.

Image: Slovenské elektrárne, a.s.

Key facts

  • Mochovce 4 reached 35% reactor power on November 12
  • Cumulative generation was 16,184.77 MWh as of November 8
  • All four Mochovce units are connected to the grid for the first time

Mochovce 4 reached 35% reactor power on November 12 at 2:35 a.m. and has generated 16.2 GWh since its first grid connection, Slovenské elektrárne said. The unit is continuing energy commissioning, with tests and measurements underway at its current power level.

After the tests are completed and evaluated, the company plans to raise reactor power to 55%, followed by 75%, 90% and 100%. The unit first supplied electricity to the grid on October 15, 2026, at about 20% power. Its connection means all four Mochovce units are now connected to the grid for the first time.