Ontario Power Generation says first Darlington SMR will miss 2030 target and cost estimate

The company expects to substantially complete its cost-and-schedule assessment by mid-2027, citing first-of-a-kind engineering and effects on construction and supply chains.

Image: World Nuclear News

Key facts

  • Unit 1 is no longer expected to meet the October 2030 commercial operation target or the previous CAD7.7 billion estimate
  • The estimate includes systems and services intended to be common to all planned units
  • Ontario Power Generation expects its assessment to be substantially complete by mid-2027

Ontario Power Generation (OPG) says the first BWRX-300 at the Darlington New Nuclear Project will not meet the previously disclosed October 2030 commercial operation target or be completed within the previously disclosed estimated cost of CAD7.7 billion. The estimate includes required systems and services that would be common to all SMRs planned for the project.

OPG attributed the expected delay and cost overrun to GE Vernova Hitachi Nuclear Energy’s ongoing engineering for its first-of-a-kind SMR, which it said is affecting construction execution and supply-chain performance. OPG is working with the supplier to complete outstanding engineering.

OPG expects to substantially complete its cost-and-schedule assessment by mid-2027. The assessment will consider engineering and construction deliverables, design maturity and timelines, first-of-a-kind complexity, market conditions including inflation and geopolitical risks, residual risks, and mitigation and recovery actions. OPG has not disclosed a replacement cost estimate or commercial operation date.