Akkuyu completes unit 4 turbine foundation pour with more than 2,240 cubic metres

The foundation is expected to take 60 days to reach design strength; Turkish regulator inspections must clear turbine-set installation.

Image: World Nuclear News

Key facts

  • Non-stop pour lasted more than a day and used nine concrete pumps
  • More than 308 tonnes of rebar was installed beforehand
  • Turbine-set components cannot be installed until regulatory inspections sign off the foundation

Akkuyu Nuclear has completed the turbine-building foundation for unit 4 at its nuclear power plant in Turkey, using more than 2,240 cubic metres of concrete. CEO Sergei Butсkikh said it is the project's fourth turbine foundation.

The non-stop pour lasted more than a day and used nine concrete pumps. More than 308 tonnes of rebar was installed beforehand, and the foundation is expected to take 60 days to reach its design strength.

The Turkish Nuclear Regulatory Authority must inspect and sign off the foundation before components of the turbine set can be installed.

2 sources

More on Akkuyu · Akkuyu Nuclear

Report an error