Containment strength and tightness tests completed at Akkuyu unit 1

The eight-day test raised air pressure to 0.46 megapascals, 15% above the 0.4-megapascal design pressure used to assess tightness.

Image: Rosatom

Key facts

  • Tests checked the containment under elevated pressure and below-atmospheric pressure
  • Rosatom says results confirmed the structure met design requirements for strength and tightness
  • Cold-and-hot run-in of the reactor plant is the next pre-startup stage, per Akkuyu Nuclear CEO Sergei Butskikh

Rosatom said on November 12 that strength and tightness tests had been completed on the reactor building’s containment at unit 1 of the Akkuyu plant, which it is building in Turkey. The results confirmed the structure met design requirements and could withstand excess internal pressure, according to Rosatom.

The tests ran continuously for eight days. Air pressure inside the containment was raised to 0.46 megapascals (MPa), 15% above the calculated pressure of 0.4 MPa used for the tightness assessment, then reduced in stages. The program also checked tightness at below-atmospheric pressure.

Akkuyu Nuclear CEO Sergei Butskikh said the results would allow the project to move soon to the next pre-startup stage, a cold-and-hot run-in of the reactor plant. He gave no date for that work.

2 sources

More on Rosatom · Akkuyu · Akkuyu Nuclear

Report an error