Estonia narrows nuclear plant search to three sites in Viru-Nigula
The planning area still covers eight municipalities, and the first site decision is due by the end of 2027.
_41535.jpg)
Key facts
- Candidate sites are Madala, Malla and Letipea; three locations in Lüg anuse municipality were ruled out for security reasons
- The spatial plan could be established in 2030 at the earliest
- Fermi Energia expects to apply for a construction permit in 2029 for a proposed two-reactor plant
Estonia’s search for a nuclear power plant site has narrowed to Madala, Malla and Letipea, all in Viru-Nigula municipality. The Ministry of Economic Affairs and Communications announced the revised list after three locations in Lüg anuse municipality were ruled out for security reasons.
The first planning stage is to select a site for the plant and its infrastructure by the end of 2027. Detailed planning and further impact assessments will follow; establishment of the spatial plan could take place in 2030 at the earliest. The planning area still covers eight municipalities because routes for electrical connections, cooling water lines, roads and other infrastructure may cross their territories.
Fermi Energia is developing a proposed plant with two BWRX-300 small modular reactors. The company expects to submit a construction permit application in 2029, targets construction to begin in 2031 and intends the first reactor to be operational by the second half of 2035.