Four steam generators delivered for Leningrad II unit 3

Installation is scheduled for 2027, and the reactor vessel is planned to be placed in position in the third quarter.

Image: Rosatom

Key facts

  • Four vessels, each 13 m long and 4.2 m in internal diameter; combined weight exceeds 1,300 tonnes
  • Eight supporting structures planned by spring 2027, requiring 85 tonnes of reinforcing steel and 370 cubic meters of concrete, per Titan-2
  • Reactor-vessel installation planned for the third quarter of 2027, per Leningrad NPP
  • First electricity from unit 3 planned for 2030, per Rosatom

Rosatom said on November 25, 2026, that four steam generators had arrived at the construction site for unit 3 of Leningrad II in Sosnovy Bor. They are the first reactor-system equipment delivered there for the unit. The cylindrical vessels will undergo incoming inspection before installation.

Each generator will produce saturated steam

Each vessel is 13 m long and has an internal diameter of 4.2 m; together, the four weigh more than 1,300 tonnes. Inside each are nearly 11,000 heat-exchange tubes, each 16 mm in diameter, creating a heat-transfer surface of 6,000 square meters.

Leningrad NPP deputy chief engineer Alexey Mochalov said the four generators are expected to produce nearly 6,500 tonnes of saturated steam per hour. The steam will drive a turbine whose rotor and blades weigh 675 tonnes, turning at 1,500 rpm.

Installation is scheduled for 2027

Rosatom said the generators are scheduled to be installed in their operating positions next year. Titan-2 program director Konstantin Khudyakov said construction crews plan to complete eight supporting structures in the reactor building by spring 2027, two for each generator. The supports will require 85 tonnes of reinforcing steel and 370 cubic meters of special concrete.

Leningrad II deputy construction director Evgeny Milushkin said work in 2027 is due to include installation of the steam generators, the pressurizer and the main circulation pumps. Installation of the reactor vessel is planned for the third quarter of that year. Work will also continue on the double containment, floors, instrumentation, safety and control systems, support systems and piping.

Unit 3 is planned to start generating in 2030

Construction of units 3 and 4 at Leningrad II began in 2022. The two VVER-1200 units are intended to replace units 3 and 4 at Leningrad NPP, which have RBMK-1000 reactors. The station’s two earlier VVER-1200 units entered service in 2018 and 2021.

Rosatom plans for unit 3 to begin supplying electricity to Russia’s grid in 2030. It forecasts annual generation of more than 8.5 billion kWh for each of the new units once they enter commercial operation.