Tianwan unit 8 completes hot tests ahead of nuclear fuel loading
Equipment inspections and regulator authorization remain before fuel loading; Rosatom plans physical startup in the first quarter of 2027.

Key facts
- VVER-1200 unit completed hot tests at temperatures above 260°C
- Equipment inspections must precede regulator authorization for fuel loading
- Physical startup planned for the first quarter of 2027, per Rosatom
- Construction of units 7 and 8 began May 19, 2021
Unit 8 at China’s Tianwan nuclear power plant has completed hot testing of its reactor systems, a required step before physical startup. Rosatom announced the result on November 25, saying the unit is preparing for nuclear fuel loading. Before fuel can be loaded, the main and auxiliary equipment in both reactor circuits must be inspected and the regulator must authorize loading.
Hot tests checked systems above 260°C
The hot run tested the reactor plant at temperatures above 260°C. The program included checks of protection systems in the first and second circuits against excessive pressure, tests of the main circulation pumps under hot operating conditions, and checks of the unit’s own power-supply systems.
Atomstroyexport’s vice president for projects in China and prospective projects, Alexey Bannik, said the tests confirmed the safe and effective operation of the equipment and systems. The company said physical startup of unit 8 is planned for the first quarter of 2027.
Russian and Chinese companies are building units 7 and 8
An intergovernmental protocol and framework contract for the two VVER-1200 units were signed in Beijing on June 8, 2018. Rosatom’s engineering division signed on the Russian side, with companies of CNNC on the Chinese side. The parties also signed technical-design and general contracts. Rosatom’s engineering division designed the nuclear island—the part of a nuclear plant containing the reactor and associated systems—and supplied key equipment for both units. Construction began on May 19, 2021. The contract value was not disclosed.
Unit 7 began power startup on October 8, 2026, and supplied its first electricity to the national grid. Rosatom said it was operating at 100% power during a 700-hour demonstration run, with guarantee tests underway to check reactor-plant parameters against contractual requirements. The four earlier Tianwan units use VVER-1000 reactors; Rosatom said they are operating and supplying electricity to the grid.
Fuel loading still needs inspection and approval
Rosatom said the next steps for unit 8 are inspections of the main and auxiliary equipment in the first and second circuits, followed by authorization from the regulator to load fuel.