Global Atomic cuts Dasa project cost estimate by US$34 million

Civil construction of the process plant is approximately 47% complete, while the approved US$414.2 million loan remains conditional.

Image: Global Atomic Corporation

Key facts

  • Dasa’s estimated capital cost is now US$743.6 million, down from US$777.6 million
  • Remaining equity requirement estimated at US$53.8 million after proceeds from the October 1 offering
  • Process plant civil construction is approximately 47% complete; acid plant steel and equipment installation has begun
  • US International Development Finance Corporation approved a facility of up to US$414.2 million, subject to conditions

Global Atomic now estimates Dasa’s capital costs at US$743.6 million, US$34 million below its previous estimate of US$777.6 million, after removing or deferring non-core expenditures, the company said in its Q3 results published November 12, 2026. After accounting for net proceeds from its October 1 equity offering, Global Atomic estimates its remaining equity requirement at US$53.8 million.

The US International Development Finance Corporation (DFC) approved a debt facility of up to US$414.2 million on September 16, comprising a term loan of up to US$397.4 million and a US$16.8 million cost overrun facility. Entry into and disbursement of the facility depend on an export route for yellowcake, an extension of the mining convention and permit, a government-to-government agreement, definitive loan documents and funding of Global Atomic’s equity portion. The company expects the loan documents by the end of Q1 2027 and says it could draw funds as early as Q2 2027 if conditions are met.

Global Atomic is pursuing offtake prepayments, capped streaming deals and subordinated debt to fund its share and limit share issuance. It says it has received verbal approval from Niger’s government to align the mining permit renewal with the loan’s 10-year term, with documentation in progress.

At Dasa, civil construction of the process plant is approximately 47% complete, and installation of steel and equipment has begun at the acid plant. Four underground mining levels in the footwall of the orebody are complete; the underground development has been underway since November 2022.