NRC approves construction permit for four-unit X-energy plant at Dow site

The permit completes safety and environmental reviews but does not authorize operation; Dow expects to consider a preliminary investment decision in 2027.

Image: X-energy, the original document

Key facts

  • Four proposed Xe-100 reactors would supply electricity and high-temperature steam at Dow’s Seadrift site
  • An NRC operating license will still be required before fuel loading and startup
  • Full-scale construction would follow Dow’s final investment decision, per X-energy
  • First NRC construction-permit approval for a high-temperature gas-cooled reactor in nearly 60 years, per X-energy

The NRC approved a construction permit for the proposed four-unit Xe-100 plant at Dow’s Seadrift Operations site in Texas, allowing the project to advance toward construction readiness, X-energy said November 9. Long Mott Energy, Dow’s wholly owned subsidiary, is the permit applicant and recipient.

The proposed plant is intended to supply electricity and high-temperature steam, replacing existing energy and steam assets near the end of their life. The NRC’s review found the design can be safely sited and constructed within an operating industrial site. Long Mott Energy submitted the application in March 2025, and the NRC set an 18-month review schedule in June 2025; X-energy said the review finished slightly ahead of schedule.

The permit does not authorize operation. The project still needs an NRC operating license before fuel loading and startup, while X-energy and Dow continue work on design finalization, supply-chain readiness and an operating-license application. X-energy said Dow expects to consider a preliminary investment decision in 2027; full-scale construction would follow Dow’s final investment decision.