NRC extension shifts Orano’s Project Ike review estimate to June 2027
Orano says the longer review will not delay enrichment operations, which it expects to begin in 2031.

Key facts
- NRC originally planned to complete its expedited review by April 30, 2027
- The parties are working toward December 14 for all responses to requests for additional information
- NRC flagged structural design criteria as a high-impact technical issue
- NRC’s review to that point suggested Project Ike and Eagle Rock share fewer similarities than anticipated
The NRC has given Orano Enrichment more time to answer questions about its Project Ike license application. The NRC had planned to complete its accelerated technical review by April 30, 2027, but now estimates completion in June 2027.
The NRC sent Orano requests for additional information (RAIs) on July 20, August 11 and August 27, expecting answers by the end of August. Orano answered about half before asking for more time on October 7; the NRC granted the extension on October 27. The two parties are working toward December 14 as the final date for all RAI responses.
The NRC classified the facility’s structural design criteria as a “high-impact technical issue” and sought more information on hydrology, fire and chemical safety, and integrated safety analysis. It also said it had not received a detailed crosswalk comparing Project Ike with Orano’s former Eagle Rock Enrichment Facility, and that the facilities appear less similar than anticipated. The NRC had expected the comparison to help it use findings from Eagle Rock’s safety evaluation in its Project Ike review.
The NRC says it will expedite parts of the review where possible. Orano says the extended review will not delay Project Ike’s enrichment operations, which it expects to begin in 2031.