Nuclear Restoration Services completes remediation of 4.2 hectares at Harwell

More than 97,000 tonnes were removed, but land delicensing and environmental-permit surrender remain.

Image: UK Nuclear Decommissioning Authority, the original document

Key facts

  • More than 97,000 tonnes of material removed during the project
  • Reuse of excavated material avoided approximately 60,000 tonnes of imports and an estimated 2,700 vehicle movements, per Nuclear Restoration Services
  • Physical remediation is complete; final regulatory steps are under way

Nuclear Restoration Services (NRS) has completed remediation of 4.2 hectares at Harwell, restoring the former liquid effluent treatment plant and adjacent sewage farm area after more than 60 years of treatment operations, the company said on November 9, 2026. NRS described it as its largest land remediation project to date.

The project removed more than 97,000 tonnes of material and tackled buried tanks, pipelines, pumping stations and concrete structures, some as deep as 10 metres. Material excavated to create a sustainable drainage pond was reused to reprofile the former treatment-plant area; NRS said this avoided importing approximately 60,000 tonnes of material and an estimated 2,700 vehicle movements. Public access has also returned to Icknield Way, a public bridleway closed during the work.

The treatment plant was built in 1948, and operations ended in 2013. NRS says the restored land is available for potential future use at Harwell Science and Innovation Campus. Physical remediation is complete, but final regulatory work is under way to delicense the land and surrender the environmental permit.

2 sources

More on Nuclear Restoration Services