Posiva tests used-fuel cask on about 3 km route to plant
The cask carried no fuel; the test checked receiving equipment and systems before commissioning.

Key facts
- First cask transport along the full route to Posiva’s encapsulation plant
- Cask docked to the handling cell; no fuel was carried
- A further test is planned, with timing not yet set
- The operating licence was granted last month, but the facilities are not yet commissioned
Posiva completed the first test transport of a used-fuel transfer cask along the route to its encapsulation plant at Olkiluoto, extending the journey from a few hundred metres to about three kilometres. The cask contained no fuel. The test checked whether the plant could receive and handle it as part of preparations for commissioning.
The cask has been used for several years to transport used fuel from Finnish nuclear power plants to the interim repository at Olkiluoto. During the test, it was loaded onto Posiva’s transfer trolley and docked to the handling cell, where fuel handling will take place once the disposal facility begins operating. Posiva said it would make minor equipment adjustments after the test. TVO also took part.
Further testing remains before operations
Posiva plans another test run, with the timing still undetermined. It will extend cask-handling tests and check the fuel transfer machine using the fuel positions of an actual cask. Procedures for the controlled area will also be activated.
The test is part of a wider commissioning program intended to establish whether the encapsulation plant is ready for production operation. Posiva applied in December 2021 for an operating licence covering the plant and the Onkalo final disposal facility. The licence was granted last month, but the facilities have yet to be commissioned.
The plant is designed to package used fuel from TVO’s Olkiluoto and Fortum’s Loviisa power plants into disposal canisters. The amount of fuel to be disposed of corresponds to approximately 3,300 canisters; once operations are fully established, Posiva plans to dispose of a maximum of 60 canisters annually.

2 sources