Sellafield strengthens supervision after ONR notice following crane-rope fall

The notice followed an April 2025 incident in which steel ropes came loose and fell during overhead-crane work.

Image: UK Office for Nuclear Regulation

Key facts

  • Sellafield clarified the Technical Oversight role and integrated it into site-wide supervision arrangements
  • Updated arrangements and training help supervisors get subject matter expert assistance
  • The notice concerned health and safety assistance, specifically supervision

Sellafield Ltd has strengthened control and supervision arrangements at its Cumbrian site after an improvement notice over health and safety assistance. The Office for Nuclear Regulation (ONR) said on November 18, 2026, that Sellafield had complied with the enforcement action.

In April 2025, contractors replacing steel ropes on an overhead crane under Sellafield’s supervision were involved in an incident in which the ropes became loose and fell to the ground. Sellafield clarified the Technical Oversight role, which supports examination, inspection, maintenance and testing, and integrated it into site-wide supervision arrangements. Supervisors also have updated arrangements and training to help them get subject matter expert assistance.

The ONR issued the notice under Regulations 7(1) and 7(5) of the Management of Health and Safety at Work Regulations 1999, concerning the provision of health and safety assistance, specifically supervision.

1 source