Texas authorizes enCore’s first Upper Spring Creek wellfield
EnCore expects extraction to start in the first week of December, but full-scale operation still needs approval for a constructed waste disposal well.

Key facts
- Authorization covers uranium extraction in the first defined wellfield area; the plant and wellfield were built ahead of approval
- EnCore expects oxygenated-water injection and extraction to begin in the first week of December, after final inspections
- Full-scale operation requires approval to operate the waste disposal well; enCore expects approval in December
The Texas Commission on Environmental Quality has authorized the first wellfield at enCore’s 100%-owned Upper Spring Creek in-situ recovery uranium project in South Texas, the company said on November 19. The authorization permits extraction in the first defined wellfield area and completes the wellfield permitting required for injection and recovery.
EnCore expects oxygenated-water injection and uranium extraction to begin in the first week of December, after final inspections. The company built the satellite ion-exchange plant and wellfield before receiving the authorization.
Full-scale operation still depends on approval to operate the constructed waste disposal well, which will handle saline water generated by wellfield operations. EnCore expects that approval in December. Uranium-loaded resin from the satellite plant will be trucked to the Rosita plant for processing into yellowcake.