Zhejiang San'ao unit 4 completes reactor-building raft foundation pour
Inspectors monitored the roughly 60-hour pour in three shifts, covering the reactor island, concrete plant and specimen room.

Key facts
- Reactor-building raft foundation pour completed at Zhejiang San'ao unit 4
- Continuous pouring lasted about 60 hours
- The East China Nuclear and Radiation Safety Supervision Station plans follow-up oversight of concrete curing, temperature monitoring and nonconformance closure
China General Nuclear’s Zhejiang San'ao nuclear power plant has completed the pour of the reactor-building raft foundation for unit 4, reaching the project’s first-concrete milestone. The East China Nuclear and Radiation Safety Supervision Station of the Ministry of Ecology and Environment said it carried out on-site oversight throughout the work to safeguard construction quality at the start of the Hualong One unit’s construction.
The pour ran continuously for about 60 hours. The station assigned inspectors to three shifts for around-the-clock patrols of the reactor island, concrete mixing plant and specimen-forming room. At the reactor island, inspectors checked concrete slump tests, temperature control before placement, vibration work and the presence of quality-control staff. In the specimen room, they monitored temperature and humidity, specimen identification, and forming and curing records. At the mixing plant, they checked concrete mix proportions and whether aggregate moisture tests were being performed.
The station said it coordinated inspection teams and prepared a special oversight plan. It also pressed the plant operator, engineering contractor, supervision contractor and construction crews to meet their quality and nuclear-safety responsibilities. Follow-up inspections will cover concrete curing, temperature monitoring for mass concrete and closure of nonconformances.