PEJ and Westinghouse-Bechtel set next equipment steps for Polish plant

The planned plant has three AP1000 reactors; earlier first-unit orders cover six nuclear-island components and four module packages from Polish firms.

Image: World Nuclear News

Key facts

  • Three AP1000 reactors planned at Lubiatowo-Kopalino
  • Six nuclear-island components included in the earlier first-unit order, per PEJ
  • Conditional purchase orders cover four module packages from Polish firms
  • US partners to support PEJ’s export-credit-agency financing negotiations

Polskie Elektrownie Jądrowe (PEJ) signed a letter of intent with the Westinghouse-Bechtel consortium to prepare for procurement of another batch of long-lead items for the first unit of Poland’s planned nuclear plant. The parties agreed to work on a mechanism for extending the scopes of contracts critical to the project schedule; the letter does not announce new orders or specify the next batch’s components.

Long-lead items are components that need to be ordered early because of their extended delivery times. PEJ said early procurement would help reduce schedule risks and keep the plant on track for commissioning. The planned plant at Lubiatowo-Kopalino will have three AP1000 reactors.

Earlier orders cover six components

In October, PEJ authorized Westinghouse to begin ordering long-lead items for the first unit. That order covers six nuclear-island components, including the reactor containment vessel and associated structural modules.

Westinghouse has placed conditional purchase orders with four Polish companies for module work: Mostostal Kielce for the CA02 Walls Module Scope, Energomontaż-Północ Gdynia SA for the CA03 Module Scope, Mostostal Kraków SA for the CA05 Walls Module Scope, and FAMAK SA for the CA20 Floors Module Scope. Earlier this month, Japan’s IHI Corporation received an order for engineering and procurement work on one containment vessel and an associated large steel module.

The new letter of intent also provides for US partners to support PEJ’s negotiations with export credit agencies over financing for the investment in power plant components. It does not give a value for the planned procurement or financing.

Engineering and construction contract remains under negotiation

Westinghouse, Bechtel and PEJ signed an 18-month engineering services contract in September 2023 to complete a site-specific design. After that agreement expired, PEJ and the consortium agreed terms and conditions for an Engineering Development Agreement in April last year. An amendment signed on December 29, 2025, continued design work on the nuclear island, turbine island and balance of plant, as well as further geological surveys.

In September, the consortium and PEJ agreed the main commercial and legal terms of the engineering, procurement and construction contract. They planned to complete negotiations by the end of this year.

Separately, Bechtel, Gdańsk University of Technology and the University of South Carolina signed a cooperation memorandum on nuclear education and workforce development. The agreement builds on Bechtel’s existing partnerships with the two universities.