Akkuyu first unit awaits authorization for hot functional testing
Alexey Likhachev hopes fuel loading will begin in December, with Turkey receiving nuclear electricity in January-February.

Key facts
- Rosatom is awaiting permission to begin testing the first unit
- Tests will use external power and fuel simulators, not nuclear fuel
- Investors could take up to 49%, subject to Turkish government approval
Rosatom is awaiting authorization to begin hot functional testing of the first unit at the Akkuyu nuclear power plant in Turkey. Rosatom chief Alexey Likhachev said at World Atomic Days in Antalya that the project was close to the next testing stage.
The tests will check equipment at normal operating parameters using an external power source, with simulators in place of nuclear fuel. They are intended to assess equipment and safety systems, as well as staff readiness. Likhachev said he hoped the tests would be successful and that fuel loading would begin in December, followed by Turkey receiving nuclear electricity in January-February.
Work continues on the station’s other three units. Russia and Turkey are also discussing the project’s financial and economic model: the intergovernmental agreement allows investors to take up to 49%, subject to Turkish government approval for investors from Turkey or other countries. Likhachev said Turkish legal entities had expressed interest and that talks were confidential.