Balakovo plant completes 2026 repair campaign 53 days ahead of planned schedule

Rosenergoatom expects the earlier completion to add nearly 1.3 billion kWh to the plant’s planned generation.

Image: Rosenergoatom, the original document

Key facts

  • Units 1, 3 and 4 underwent scheduled maintenance
  • More than 40 modernization measures completed
  • All four units are operating

Balakovo nuclear power plant completed its 2026 repair campaign 53 days ahead of the planned duration, Rosenergoatom said on November 16. The company said the earlier completion would allow the plant to generate nearly 1.3 billion kWh above plan.

The campaign covered scheduled maintenance on units 1, 3 and 4, with nuclear fuel reloaded in all three. Unit 3’s repair, scheduled for 166 days, finished 39.2 days early and included replacing two steam generators. Unit 1 finished its 35-day planned repair eight days early; work included loading three fuel assemblies with mixed-oxide fuel. Unit 4’s repair finished six days early.

More than 40 modernization measures were completed during the campaign. Rosenergoatom said all four units are now operating.