Deep Yellow pushes Tumas final investment decision beyond Q4 2026
Detailed engineering reached 85% and civil and concrete works began, while debt financing remains subject to credit approvals and documentation.

Key facts
- Deep Yellow says current equity market conditions do not support a final investment decision in Q4 2026
- Detailed engineering at Tumas reached 85% completion
- Civil and concrete contractors mobilized and began work at the site
- Cash and cash equivalents totaled A$144.7 million at September 30, 2026
Deep Yellow will not make a final investment decision (FID) on its Tumas uranium project in Q4 2026, saying current equity market conditions do not support that target, the company said in its September-quarter activities report. Full construction remains ahead of the FID.
Detailed engineering reached 85% completion, and civil and concrete contractors mobilized to site and started work during the quarter. Debt financing discussions with Nedbank are progressing toward credit approvals, but financial close remains subject to customary conditions, including definitive financing documents.
Deep Yellow had A$144.7 million in cash and cash equivalents at September 30, down from A$160.0 million at the end of the June quarter.