NRC seeks comment on 20-year Crownpoint uranium license renewal

The draft review preliminarily finds no significant environmental impacts; NuFuels still needs a renewed license and other approvals before construction.

Image: ANS Nuclear Newswire

Key facts

  • Proposed license renewal would authorize construction and operation for 20 years, if granted
  • Draft environmental assessment preliminarily finds no significant impacts
  • Project areas cover more than 2,500 acres; estimated disturbance is about 478 acres
  • License limits annual yellowcake production to 3 million pounds
  • Public comments are due December 21, 2026

The Nuclear Regulatory Commission (NRC) has opened a public comment period on its draft environmental assessment and draft programmatic agreement for NuFuels’ proposed Crownpoint Uranium Project license renewal. The NRC’s preliminary finding is that renewing the license for 20 years would not significantly affect the human environment; the agency has not yet decided whether to renew it. Comments are due December 21, 2026.

The application concerns Source and Byproduct Materials License SUA-1580. If renewed, it would allow NuFuels to construct and operate in situ recovery facilities on four project areas in McKinley County, New Mexico: Crownpoint, Unit 1, and Church Rock Sections 8 and 17. In situ recovery uses wellfields to recover uranium from underground deposits. Construction has not started.

The project has defined land and production limits

The four license areas cover more than 2,500 acres, while the area expected to be disturbed over the project’s estimated life is about 478 acres. The proposed system includes a central processing plant, two satellite ion-exchange facilities, sequentially developed wellfields, evaporation ponds and support infrastructure. Uranium would be recovered from the Westwater Canyon Member of the Morrison Formation, at an average depth of 1,840 feet.

License SUA-1580 sets a maximum processing flow rate of 4,000 gallons per minute at each of the Church Rock, Unit 1 and Crownpoint areas, and caps total yellowcake production at 3 million pounds annually. The proposed land use at Church Rock Section 8 has risen from 160 acres to 174.5 acres. NuFuels is remediating parts of Church Rock Section 17 under the authority of the Environmental Protection Agency and the Navajo Nation Environmental Protection Agency; the areas were contaminated by past mining at the Old Church Rock Mine site.

Renewal would not authorize construction on its own

Before construction, NuFuels must obtain applicable permits and approvals from federal agencies, New Mexico, the Navajo Nation and local authorities. The NRC also says renewal depends on NuFuels demonstrating it can meet agency requirements for construction, operation, aquifer restoration and decommissioning.

After wellfield operations end, the company would restore groundwater in the production zones to required standards. It would then submit a decommissioning plan for NRC approval before reclamation and decommissioning. If restoration or decommissioning continued beyond the proposed 20-year renewal period, NuFuels would need to seek another renewal.

The NRC’s draft assessment considers impacts including groundwater, ecological resources, cultural and historic sites, public health and waste management. It draws in part on earlier NRC environmental reviews. For the proposed action, NRC staff preliminarily found impacts would not be significant across the resources assessed. The agency says the U.S. Fish and Wildlife Service concurred that the project may affect, but is not likely to adversely affect, the southwestern willow flycatcher and yellow-billed cuckoo.

Cultural review and license challenges remain

The project areas lie within the external boundaries of the Navajo Nation, and some portions are Navajo trust lands. The draft programmatic agreement, developed as part of the NRC’s historic-preservation review, is among the NRC, the Navajo Nation, its Tribal Historic Preservation Officer, the Bureau of Land Management and NuFuels.

New Mexico’s Department of Justice petitioned to intervene in the renewal proceeding in July 2026. It raised environmental and safety concerns, including groundwater restoration and the project’s financial guarantees. The NRC found some of the state’s contentions admissible, then changed its position on the financial-guarantee contention before an October hearing, according to the account of the proceeding. The state had not filed new or amended contentions as of that account.

The NRC’s draft finding is preliminary, and the license renewal is proposed rather than approved. NuFuels must still secure the required permits and authorizations before it can begin construction.