PSI to demolish building of Switzerland’s first research reactor
About 180,000 measurements found the remaining concrete below legal release limits, allowing demolition as a conventional building.

Key facts
- Demolition of Saphir’s remaining concrete structure is expected to take about three months, per PSI
- Around 180,000 measurement points were checked over roughly 250 days of pure measurement time
- Reactor internals, underwater installations and the pool had largely been removed by 2008
- PSI is also dismantling the larger, more complex Diorit research reactor
The Paul Scherrer Institute (PSI) plans to demolish the remaining concrete structure of the Saphir research reactor in the coming months. When the building is gone, it will be the first former nuclear facility in Switzerland to be completely dismantled, including its building.
The concrete has been cleared for demolition
Saphir’s reactor internals and pool have been largely removed, leaving a hollowed-out structure. Before demolition, PSI measured the concrete for radioactive contamination and checked areas where radioactive activation might have penetrated the material. The institute reports around 180,000 measurement points across the building. Each square meter was measured for about two minutes, amounting to roughly 250 days of pure measurement time.
Where readings were too high, PSI removed the affected material and measured again. The remaining concrete was found to be below legal release limits, so the building can be demolished like a conventional structure. PSI plant manager Sophie Harzmann expects a green meadow to be in place in about three months.
Saphir operated from 1957 to 1993
Built in 1955 at Oak Ridge National Laboratory in the US state of Tennessee, Saphir was flown to Geneva for the first United Nations Atomic Energy Conference, where it served as a demonstration reactor. Switzerland bought it for 250,000 dollars, including fuel, mechanics and a control room, and built a reactor building at Würenlingen, in Aargau.
Saphir started up on April 30, 1957, and remained in operation until the end of 1993. The swimming pool-type reactor used water for cooling and shielding; its characteristic blue glow came from Cherenkov radiation produced when fast charged particles passed through the water. It was also used for neutron research: the first neutron diffraction experiments on a single crystal at Saphir took place in 1960.
PSI submitted its decommissioning request in 1998, and dismantling began in 2002. By 2008, the reactor’s internal components, underwater installations and pool had largely been removed.
PSI is also dismantling Diorit
PSI is using experience from Saphir’s dismantling for work on the former Diorit research reactor. Diorit is larger and more complex, and PSI plans to automate more of the measurement and documentation work there. An experimental incineration plant that once burned low-level radioactive waste is also slated for demolition.